Ten steps, in order, on every new sewer line job

The new sewer line process in ten steps, from camera scope and locates to permits, excavation, inspection, backfill and records, with Calgary and Alberta rules.

A conceptual house-to-street installation sequence showing utility locates, a protected trench, pipe placement and restored surfaces, illustrating the ordered stages of a new sewer project.
Process / field studyTen steps, in order, on every new sewer line jobConceptual illustration, not to scale or a site assessment.Read the guide
Short answer

A new sewer line job runs in ten steps: an on-site camera scope, utility locates, a route plan, a written line-item quote, permits, a protected excavation, installation of the new pipe, an inspection of the open trench, backfill in compacted lifts, and cleanup with records. Skipping or reordering any of them, especially inspecting after backfill, is where most problems start.

Key takeaways
  • Steps one to five are preparation and usually take longer than the dig itself.
  • Locates need at least three full working days of notice in Alberta, and your own sewer line is not marked by the one-call.
  • A written quote should itemise pipe, method, permits, restoration and exclusions before any permit is pulled.
  • The trench is inspected open, before backfill: never covered blind.
  • The job is finished when you hold the after-video, the inspection record and an as-built, not when the machine leaves.
A sewer camera reel, monitor and locator on a front lawn in autumn
IllustrationA push-camera reel and monitor with the locator receiver, set up on a front lawn.
The ten steps of a new sewer line project in four phasesA timeline of ten steps grouped into decide, permit, dig and connect. Below it, bars mark the common waiting points: at least three full working days of notice for utility locates in Alberta, permit processing, and booking the inspection before the trench is backfilled. DECIDE 01SCOPE02LOCATE REQUEST03ROUTE PLAN04WRITTEN QUOTEPERMIT 05PERMITSDIG 06EXCAVATION07INSTALLATIONCONNECT 08INSPECTION09BACKFILL10CLEANUP WHERE THE WAITS ARE Locates: at least 3 full working days' notice (Utility Safety Partners) Permits: processing time set by the permit office Inspection before backfill ORDER, NOT TIME SCALE · WEATHER, DEPTH AND THE CITY SIDE STRETCH ANY STEP MOST OF THE CALENDAR IS PREPARATION; THE DIG ITSELF IS OFTEN A FEW WORKING DAYS
Fig. 1Ten steps in four phases. The waits are usually paperwork and locates, not digging: plan for them before the dig date is promised.

01 /Why does the order of the steps matter?

A new sewer line is not a mystery, but it is a sequence. Each step produces something the next one depends on: the scope produces footage for the quote, the locate produces marks for the route plan, the permit allows the dig, and the inspection allows the backfill. Doing them out of order either wastes money, like quoting without footage, or hides problems, like backfilling before an inspection.

The ten steps of a new sewer line project in four phasesA timeline of ten steps grouped into decide, permit, dig and connect. Below it, bars mark the common waiting points: at least three full working days of notice for utility locates in Alberta, permit processing, and booking the inspection before the trench is backfilled. DECIDE 01SCOPE02LOCATE REQUEST03ROUTE PLAN04WRITTEN QUOTEPERMIT 05PERMITSDIG 06EXCAVATION07INSTALLATIONCONNECT 08INSPECTION09BACKFILL10CLEANUP WHERE THE WAITS ARE Locates: at least 3 full working days' notice (Utility Safety Partners) Permits: processing time set by the permit office Inspection before backfill ORDER, NOT TIME SCALE · WEATHER, DEPTH AND THE CITY SIDE STRETCH ANY STEP MOST OF THE CALENDAR IS PREPARATION; THE DIG ITSELF IS OFTEN A FEW WORKING DAYS
Fig. 2Ten steps grouped as decide, permit, dig and connect. The waiting sits mostly in the first two phases.

The same ten steps apply to a lateral replacement, a new service connection and renovation-driven work. What changes is who is involved at each step and how long it takes.

02 /Steps 1 to 4: how is a new line scoped, located, planned and quoted?

  1. 01 Scope

    An on-site walk-through and a recorded camera inspection confirm the failure or the need for a new connection. A good scope also locates the line: a sonde in the camera head lets the technician mark the route and depth on the surface. You should receive the footage, not just a verdict.

  2. 02 Locate utilities

    A locate request goes to Utility Safety Partners, Alberta's one-call service, so gas, power, telecom and other registered utilities are marked before digging. The service asks for at least three full working days of notice for a routine request, and five for large projects; in September 2026 its site warned of 5 to 10 business days during high volume. Customer-owned lines, including your sewer and water service, are not registered with it and need a private locator.

  3. 03 Route plan

    Depth, grade and the connection point are mapped against the marked utilities to avoid conflicts and minimise surface disruption: where the trench or pits go, where the machine and spoil sit, how crossings are exposed, and whether a tree root zone or structure forces a change.

  4. 04 Written quote

    A line-item quote with pipe size and material, method, length, the cleanout, permits, restoration scope item by item, the schedule and the exclusions. This is the document you compare, so every quote should describe the same scope.

Sewer camera inspection with locatorA push camera travels through the lateral from a cleanout, lighting the pipe while a footage counter records distance. A sonde in the camera head emits a signal a surface locator uses to mark position and depth. LOCATOR: POSITION + DEPTH REC ●012.4 m LIGHTED HEAD + FOOTAGE COUNTERACCESS: CLEANOUT
Fig. 3The scope: a camera on a push rod, a lit view down the pipe, a footage counter and a sonde that lets the route and depth be marked on the surface.

If a camera scope and a second opinion are all you need at this stage, the New Line or Repair? Check helps you read the footage before committing to step five.

03 /Step 5: which permits are needed?

Permits are pulled and posted before work begins. In Calgary, the City's trades permits page lists replacing water and sewer lines in or around the home as work that needs a plumbing permit. A homeowner permit is only available to an owner who lives in the home and does the work personally; when a contractor does the work, the contractor applies. Any digging into a City road right-of-way needs an excavation permit, which the City says can be applied for up to two weeks before the start date and normally takes up to two business days to process, or up to ten where recently paved roads are affected.

Outside Calgary, the Government of Alberta says permits are available through municipalities accredited to administer the Safety Codes Act, and through accredited agencies overseen by the Alberta Safety Codes Authority in municipalities that are not accredited. The Alberta service area page explains what to ask in the towns and counties around Calgary.

Sewer camera view down a clean white ABS plastic pipe
IllustrationCamera view of a sound ABS plastic line: smooth walls, water running along the bottom, nothing to report.

04 /Steps 6 and 7: how are the excavation and installation done?

  1. 06 Excavation

    The trench or pits are dug with protection that matches depth and soil. In Alberta, once a worker is in an excavation deeper than 1.5 m and closer to the wall than its depth, the OHS Code requires cut-back walls, a temporary protective structure or both, with spoil at least 1 m back from the edge. Marked utilities within the hand-expose zone are uncovered by hand first. Driveways and lawns that are staying are protected.

  2. 07 Installation

    The old pipe is removed where conditions allow, or capped and recorded where a section has to be abandoned. The new pipe, usually PVC, is laid on proper bedding at a steady grade and connected at both ends: the house stub and the municipal connection. A cleanout is added near the foundation if there is not a usable one.

Open-cut sewer trench in cross-sectionA trench cut across the line: spoil piled back from the edge, sloped or shored walls, a granular bedding layer under the new pipe, initial backfill around it, and native backfill compacted in lifts up to restored grade. SPOIL KEPT BACK ① BEDDING ② NEW PIPE ③ INITIAL BACKFILL ④ COMPACTED LIFTS DEPTH DEEP TRENCHES NEED SLOPING OR SHORING UNDER PROVINCIAL OHS RULES CROSS-SECTION · NOT TO SCALE
Fig. 4An open-cut trench in section: protected walls, bedding under the pipe, initial fill around it and compacted lifts to grade.

What each protection option looks like, and how restoration is planned alongside the dig, is in excavation and restoration.

05 /Steps 8 to 10: how is the new line inspected, backfilled and handed over?

  1. 08 Inspection

    The inspector sees the pipe with the trench open, before any backfill, and checks the bedding, grade and connections. For a Calgary homeowner permit the City lists a rough-in inspection once drainage and venting are installed and a final inspection once fixtures are ready. Whoever holds the permit books the inspection.

  2. 09 Backfill

    Bedding material around the pipe, compacted lifts to bring the trench back up, and suitable fill to finish grade. This is the step that decides whether the surface settles later.

  3. 10 Cleanup and records

    A site walk-through, an after-video of the new line from the cleanout to the connection, the inspection record, an as-built sketch with depth and cleanout locations, and a written restoration plan for anything not finished the same day.

Step ten is the one most often skipped, and the one that protects you longest. Handover and warranty lists what the closing package should contain and what a warranty on a new line should say.

06 /How long does the whole process take?

For a single-family lateral, the dig itself is usually one to three working days once permits and locates are in hand, and one to two for trenchless work. The preparation before it, from first scope to permit, often takes a few weeks for planned work, depending on how quickly quotes come back, how busy the locate service is and how long the permit takes. Winter, deep lines, long runs and City-side work stretch every step.

Where the time goes (planning guide)
StepTypical timeWhat controls it
Scope and quotesDays to a couple of weeksContractor availability, second opinions
LocatesAt least 3 full working days of noticeUtility Safety Partners volume, season
PermitsDays, longer with road right-of-way workThe permit office
Excavation and installation1–3 working days open cut; 1–2 trenchlessDepth, length, surfaces, weather
InspectionBooked around the open trenchInspector scheduling
Backfill and restorationSame day to weeksConcrete cure, landscaping, season

Emergencies compress the front of the process but do not remove it: locates and permits still apply, although emergency arrangements exist, and your contractor should explain them. To see the steps laid out with your own length, depth and surfaces, use the project planner, and when you want the process priced, send your details.

FAQQuestions people ask

What is the first step in getting a new sewer line?

A recorded camera inspection with a locate of the line's route and depth. Every later step, from the quote to the permit, depends on what the footage shows.

Who requests the utility locates for a sewer line job?

Usually the contractor, through Utility Safety Partners, with at least three full working days of notice. Ask to see the ticket, and ask who is arranging the private locate for your own lines.

Can the inspection happen after the trench is filled in?

It should not. The inspector needs to see the pipe, bedding and connections with the trench open. Backfilling first means nobody can confirm what went in the ground.

How many days will I be without a toilet during a sewer line replacement?

Plan for no drains for part of the time on site, from several hours to a day or more on open-cut jobs. Ask the contractor for the no-use window in writing.

What records should I get at the end of a new sewer line job?

An after-video, the permit and inspection record, an as-built sketch with depth and cleanout locations, the warranty in writing and the restoration plan for anything still to finish.

NETWORKGo deeper across the HAUSE Sewer network

Request quotes

Describe the problem once. Get a straight answer.

Send the symptoms and anything you already know — age of the house, what a camera found, what you have been quoted. The HAUSE Sewer desk replies with next steps and, where available, a local contractor for the job.

Sewage backing up right now? Stop using water, keep people away from the water, and do not touch electrical equipment near it.

Tell us about the job

Free request. We read every one and reply by email or phone.

HAUSE Sewer is an independent network, not a contractor. See our privacy notice.

The HAUSE Sewer network

One sewer line, every angle.