New Sewer Line Project Planner

Plan a new sewer line in Calgary or Alberta: the ten steps, locate and permit lead times, trench-protection rules, days on site and a 2026 CAD planning range.

01SCOPE02APPROVALS03INSTALL04HANDOVER
Field reference / schematicNew Sewer Line Project PlannerConceptual illustration, not to scale. Use the detailed diagrams and cited requirements below for the full explanation.
Short answer

The planner turns nine facts about your project into a planning range in Canadian dollars, the number of working days on site, and the ten steps in order with the Calgary or Alberta rule that applies at each one: utility locates, permits, trench protection, inspection and records. It uses the HAUSE network's published cost rates, so its numbers agree with the cost pages, and it lists what the range leaves out.

Key takeaways
  • Open cut is priced at $500–$1,100 per metre plus $4,000–$8,000 setup, adjusted for depth; trenchless at $400–$1,100 per metre plus $3,000–$8,000 for setup and pits.
  • Surface restoration is added only for open cut: landscaping $500–$2,000, concrete $1,500–$5,000, a finished basement floor $2,000–$6,000.
  • City-side work, municipal connection fees and abandoning an old service are listed as not included, because municipalities set them.
  • Locates need at least three full working days of notice through Utility Safety Partners, and your own sewer line is never marked by that service.
  • Past 1.5 m deep, Alberta's OHS Code requires trench protection for workers near the wall.
Free tool · runs in your browser

New Sewer Line Project Planner

A new white PVC sewer pipe laid on granular bedding in a trench
IllustrationA new PVC lateral on proper granular bedding, checked for grade before backfill.
The ten steps of a new sewer line project in four phasesA timeline of ten steps grouped into decide, permit, dig and connect. Below it, bars mark the common waiting points: at least three full working days of notice for utility locates in Alberta, permit processing, and booking the inspection before the trench is backfilled. DECIDE 01SCOPE02LOCATE REQUEST03ROUTE PLAN04WRITTEN QUOTEPERMIT 05PERMITSDIG 06EXCAVATION07INSTALLATIONCONNECT 08INSPECTION09BACKFILL10CLEANUP WHERE THE WAITS ARE Locates: at least 3 full working days' notice (Utility Safety Partners) Permits: processing time set by the permit office Inspection before backfill ORDER, NOT TIME SCALE · WEATHER, DEPTH AND THE CITY SIDE STRETCH ANY STEP MOST OF THE CALENDAR IS PREPARATION; THE DIG ITSELF IS OFTEN A FEW WORKING DAYS
Fig. 1Ten steps in four phases. The waits are usually paperwork and locates, not digging: plan for them before the dig date is promised.

01 /What does the New Sewer Line Project Planner ask?

Nine inputs describe the job. You can answer most of them from a camera report and a walk around the yard; where you cannot, the planner tells you what the unknown does to the result.

  1. Project: replace the existing sewer lateral, a new service for an infill or new build, or a renovation, addition or suite upgrade.
  2. Method: open cut, trenchless (bursting or lining), or not decided yet.
  3. Length of the private line: a slider from 4 to 40 m, starting at 15 m.
  4. Depth to the pipe at its deepest: under about 1.5 m, about 1.5–2.5 m, over about 2.5 m, or not sure.
  5. What the route crosses (tick all): lawn or sod, landscaping, trees or a fence, a driveway, walk or other concrete, a finished basement floor.
  6. Usable cleanout: yes, or no or not sure.
  7. City-side work: no, or yes or not sure.
  8. Season: spring to fall, or winter.
  9. Location: the City of Calgary, or elsewhere in Alberta.

Press Show my result. After the first result, changing any input updates it at once, which makes the planner useful for what-ifs: the same line with and without a driveway, or open cut against trenchless.

02 /How is the planning range calculated?

The range is built in layers, and every layer is printed under "What built this range" so nothing is hidden. The per-metre and setup figures are the same planning rates used by the network's cost page and by the sewer cost estimator on SewerQuotes.com, so a number here should never contradict a number elsewhere on the network.

Planner rates (CAD, 2026 planning estimates, as coded)
LayerLowHighWhen it applies
Open cut: setup$4,000$8,000Method = open cut
Open cut: per metre$500$1,100Multiplied by the length
Depth factor (open cut)×0.9 shallow×1.3 deepTypical and not sure = ×1.0
Trenchless: setup and pits$3,000$8,000Method = trenchless
Trenchless: per metre$400$1,100Multiplied by the length
Landscaping, trees or fence$500$2,000Open cut, if ticked
Driveway, walk or concrete$1,500$5,000Open cut, if ticked
Finished basement floor$2,000$6,000Open cut, if ticked
Lawn or sod$0$0Basic topsoil and seed is usually part of backfill
New cleanout$600$2,500No usable cleanout
Backwater valve, new construction$800$2,500New service project, where required

When the method is not decided, the low end is the cheaper of the two methods and the high end is the dearer, and ticked surfaces raise only the top of the range, because trenchless would avoid them. When the method is trenchless, surfaces are not added at all and the result says so: lining and bursting restore pits, not a trench, but a sag or a new route still needs digging.

Three worked checks, straight from the code. The defaults (15 m, open cut, typical depth, lawn, cleanout present, Calgary) give $11,500 – $24,500. Twenty metres trenchless gives $11,000 – $30,000. Twenty metres open cut at deep depth under lawn and a driveway, with no cleanout, gives $20,300 – $46,500: (4,000 + 10,000) × 1.3 + 1,500 + 600 at the low end and (8,000 + 22,000) × 1.3 + 5,000 + 2,500 at the high end.

03 /What do the ten steps in the result say?

The steps follow the same order as the ten-step process: scope, utility locates, route plan, written quote, permits, excavation, installation, inspection, backfill, cleanup and records. Four of them change with your answers.

  1. Utility locates

    Always the same text: request through Utility Safety Partners at least three full working days before digging. In September 2026 the service's own site warned that response times could run 5 to 10 business days because of high volume. Customer-owned lines, such as your sewer and water service, are not registered with the service, so a private locator is needed.

  2. Permits in Calgary

    The City's homeowner page lists replacing water and sewer lines in or around the home as work that needs a plumbing permit, and allows a homeowner permit only when the owner lives in the home and does the work. Digging into a City road right-of-way needs an excavation permit: the City says you may apply up to two weeks before the start date and that standard applications take up to two business days. For a new service, the planner adds that the City requires connections from the property line to be installed by contractors on its approved indemnified list and inspects them.

  3. Permits elsewhere in Alberta

    The province says permits come from municipalities accredited to administer the Safety Codes Act, or from accredited agencies overseen by the Alberta Safety Codes Authority where a municipality is not accredited. Road or boulevard work needs the municipality's own permission.

  4. Excavation

    For a typical or deep line, the planner states the Alberta OHS Code Part 32 rules: protection past 1.5 m deep for a worker closer to the wall than the depth (section 450), spoil at least 1 m back from the edge (section 453), and, for deep lines, engineer-designed protective structures past 3 m (section 456). For a shallow line it reminds you to confirm the real depth before assuming the rule does not apply.

How a deep sewer trench must be protected in AlbertaThree trench sections. Hard and compact soil: vertical walls no higher than 1.5 m at the bottom, cut back above that at not less than 30 degrees from vertical, with the spoil pile at least 1 m back from the edge. Soil likely to crack or crumble: the same, at 45 degrees. Any soil: a temporary protective structure such as shoring or a trench box, engineered when deeper than 3 m. CUT BACK · 30°hard and compact soil ≥1 m CUT BACK · 45°likely to crack or crumble PROTECTIVE STRUCTUREshoring or trench box 1.5 m ABOVETHE BOTTOM PROTECTION REQUIRED PAST 1.5 m DEEP WHEN A WORKER IS CLOSER TO THE WALL THAN THE DEPTH (s. 450) SOFT, SANDY OR LOOSE SOIL: SLOPED FROM THE BOTTOM AT 45° OR MORE (s. 451) SPOIL ≥ 1 m BACK, FACE ≤ 45° (s. 453) · EXIT WITHIN 8 m (s. 455) PROTECTIVE STRUCTURES OVER 3 m DEEP: DESIGNED BY A PROFESSIONAL ENGINEER (s. 456) ALBERTA OHS CODE, PART 32 · SECTIONS NOT TO SCALE
Fig. 2The three protection options the planner refers to. Which one a crew uses depends on soil, depth, room on the lot and the equipment.
A locator receiver held over a lawn with a pink paint mark
IllustrationA locate and mark: the receiver finds the sonde behind the camera head and the spot is painted with a depth.

04 /How many days on site, and what is left out?

Days on site are working days once permits and locates are in hand: 1–3 for open cut or an undecided method, 1–2 for trenchless, and one more at the low end and two more at the high end in winter. These are the same planning spans the network uses for replacement timelines. They exclude the weeks of preparation before the dig, and the result reminds you to expect no drains for part of the time on site.

The "Not in the range" list is as important as the range:

  • City-side work (when you answered yes or not sure): from $0 where the municipality does its side to $15,000 or more with a road cut and traffic control. Confirm with the municipality; in Calgary, call 311.
  • Municipal fees for a new service: application and connection fees and abandoning the old service are set by the municipality.
  • Suite upgrades: a normally open backwater valve may not serve more than one dwelling unit, per a City of Calgary advisory from October 2022, so ask how each unit is protected.
  • Winter: frost work and often temporary restoration until spring, which should be priced as its own line.
  • Permits: usually inside the contractor's price; SewerQuotes.com lists them at about $150 to $1,000 or more. For Calgary the result adds the homeowner plumbing permit fee the City published in September 2026: $112 plus a 4 percent Safety Codes Council fee, $116.50 in total.

05 /What are the limits of the planner?

The planner does not know your soil, groundwater, the exact depth at each end, how far the machine can reach, or whether a tree root plate, gas service or retaining wall sits on the route. It cannot tell you whether trenchless is possible, only what it would cost if it is; the New Line or Repair? Check and the footage decide that. It uses one per-metre rate for the whole length, while real quotes often charge the first metres at the foundation and the last metres at the connection differently.

Rules change. Every rule in the result is summarised as the official source stated it in September 2026 and is cited below; confirm permit requirements with the permit office and locate timing with Utility Safety Partners before you commit to dates. When the plan looks right, send it with your footage so contractors quote the same scope, and read what the dig does to your yard in excavation and restoration.

FAQQuestions people ask

Why does the planner price trenchless without any surface restoration?

Because lining and bursting work through pits or existing access, not a full trench. The pits still need restoring, and that is inside the setup figure. If the footage shows a sag or a route change, part of the job is open cut anyway.

Can I get a homeowner plumbing permit in Calgary and hire a crew to do the dig?

The City's page says a homeowner cannot pull a permit on behalf of the person or company doing the work. If a contractor is doing it, the contractor applies.

Does the range include the City's side of the connection?

No. City-side work and municipal connection fees are listed separately because municipalities set them and they vary from nothing to a large share of the job.

How far ahead should I request utility locates?

At least three full working days before digging for a routine request, per Utility Safety Partners, and longer in the busy season. Your contractor usually requests them; ask to see the ticket.

Why does the planner mention 1.5 metres so often?

That is the depth at which Alberta's OHS Code requires protection for a worker in an excavation who is closer to the wall than the depth. The sonde depth on your camera locate tells you which side of that line your trench will be.

NETWORKGo deeper across the HAUSE Sewer network

Request quotes

Describe the problem once. Get a straight answer.

Send the symptoms and anything you already know — age of the house, what a camera found, what you have been quoted. The HAUSE Sewer desk replies with next steps and, where available, a local contractor for the job.

Sewage backing up right now? Stop using water, keep people away from the water, and do not touch electrical equipment near it.

Tell us about the job

Free request. We read every one and reply by email or phone.

HAUSE Sewer is an independent network, not a contractor. See our privacy notice.

The HAUSE Sewer network

One sewer line, every angle.